Drought and seawater intrusion cut Banjarmasin's raw water supply by about 30 percent in September. As fresh water returns to the network, the city is putting forward a 1.1 million cubic metre reservoir, and the numbers show why raw water storage is worth treating as an asset.

At a glance
30%
Fall in raw water available for treatment in Banjarmasin
8,000 mg/L
Salt level recorded at the Sungai Bilu intake
1,900 m³/h
Shortfall between normal requirement and available supply
1.1 million m³
Proposed reservoir capacity for a strategic water reserve

Banjarmasin is coming through a difficult month for its water supply, and it is coming through with a clearer idea of what the city needs next. A long dry season lowered river flows, seawater pushed up the Martapura River, and the salt reached the intake that feeds one of the city's two main treatment plants. By the end of September, the raw water available for treatment had fallen by about 30 percent.

The response is now shifting from emergency to planning. On 27 September, the regional water utility PT Air Minum (PAM) Bandarmasih reported that raw water conditions had improved enough to stop distributing saline water. On 29 September, Mayor H. Muhammad Yamin HR inspected the treatment facilities with Banjarmasin Police Chief Kombes Pol Riza Muttaqin and PAM Bandarmasih Director Zulbadi, and put forward a reservoir of about 1.1 million cubic metres as a long term reserve. The episode offers a useful case in how a city can put a value on raw water storage.

How the salt reached the taps

Banjarmasin draws raw water from two main sources. Treatment plant IPA 1 in the Sungai Bilu area takes water from the Martapura River and has a capacity of 600 litres per second. IPA 2 in the Pramuka area draws from the Tabuk River, around 11 kilometres away, with a capacity of 1,750 litres per second. Irrigation channels normally add a third source, but in September they were not functioning because of the drought.

As river flows dropped, tidal seawater moved further inland. Berita Borneo reported salt levels at the Sungai Bilu intake reaching 8,000 milligrams per litre on 10 September, well beyond what the treatment process can handle. PAM Bandarmasih supervisor Murjani explained at the time that water with that level of salt could not be processed. The utility reported that its clean water production capacity had fallen by more than half, and more than 150,000 customers across the city were affected.

From 22 September, the utility moved to an emergency distribution arrangement. In the whole of Banjarmasin Barat and in parts of Banjarmasin Tengah and Banjarmasin Utara, piped water was supplied for bathing, washing, and sanitation only, not for drinking or cooking. Jejakrekam reported that around 70 percent of residents surveyed in the three districts agreed to the scheme, which kept water flowing for household sanitation while drinking water came from other sources.

The water balance in numbers

The most useful single figure is the hourly balance. PAM Bandarmasih told Kalimantan Post that normal operations need 7,500 cubic metres of water per hour, while 5,600 cubic metres per hour were available, leaving a shortfall of 1,900 cubic metres per hour.

The issue is not the capacity of the treatment plants. It is the raw water available to them. Mayor H. Muhammad Yamin HR, Banjarmasin

The plant figures support the mayor's point. Converted to hourly terms, IPA 1 at 600 litres per second can treat about 2,160 cubic metres per hour, and IPA 2 at 1,750 litres per second about 6,300 cubic metres per hour. Together that is roughly 8,460 cubic metres per hour of treatment capacity, comfortably above the 7,500 cubic metre requirement. The constraint sits upstream of the plant, in the quantity and quality of raw water.

That distinction matters for investment. A city facing a treatment bottleneck needs a larger plant. A city facing a raw water bottleneck needs storage, catchment protection, and alternative intakes. Banjarmasin's figures point clearly to the second.

From emergency supply to a strategic reserve

While raw water was short, the city and the utility kept supply moving through several measures. Tanker trucks served neighbourhoods at the ends of the network. Distribution schedules were adjusted to make the best use of available water at set hours. Additional collection points were set up at village offices and community health centres. Fresh water from IPA 2 was maximised across all service areas, with some zones receiving lower flow and pressure. Members of the Banjarmasin DPRD, including Hj. Neli Listriani and Tugiatno, asked the utility to consider billing relief for affected customers and to deliver tanker water proactively, as Kalselpos reported.

The longer term answer the mayor has put forward is a reservoir, or embung, of approximately 1.1 million cubic metres, discussed with the Governor of South Kalimantan. The city government notes that the plan is still at the discussion stage and not yet in implementation, and no cost has been published.

A simple calculation shows what that storage would represent. At the September shortfall of 1,900 cubic metres per hour, 1.1 million cubic metres would cover the gap for roughly 580 hours, or about 24 days. Measured against the full normal requirement of 7,500 cubic metres per hour, it equals roughly six days of the city's entire treated supply. These are illustrations of scale, not design figures, but they show that a reservoir of this size would be a meaningful buffer against a repeat of this September.

Putting a value on raw water

Raw water rarely appears on a balance sheet, and its value only becomes visible when it runs short. The September episode generated real costs that a valuation can capture: tanker operations, extra distribution effort, lost production from IPA 1, the household cost of buying drinking water, and the revenue implications of any billing relief. Set against those costs are the benefits of a reserve: avoided emergency spending, continuity of service to more than 150,000 customers, and protection of public health.

A second layer of value sits upstream. The flow of the Martapura and Tabuk rivers in the dry season depends on the condition of their catchments, including forest cover, peatland, and wetland storage. Mapping those catchments with remote sensing, pairing the maps with river flow and salinity monitoring at the intakes, and valuing the water regulation service they provide would give the city and the province a clearer basis for deciding how much to invest in storage and how much in catchment protection.

Sirkularium's view

Banjarmasin's response shows a city learning quickly. The utility communicated clearly, residents largely accepted a sanitation-only arrangement during the peak, saline distribution stopped as soon as conditions allowed, and the mayor has moved the conversation toward a permanent reserve. The candid framing that the problem is raw water rather than plant capacity is exactly the right starting point for sound investment.

For the city, the province, and PAM Bandarmasih, three steps would turn this September into lasting resilience. First, record the costs of the episode in one place, including tankers, lost production, and any relief granted, so that the reservoir business case rests on observed figures rather than estimates. Second, install continuous salinity and flow monitoring at both intakes, which would give early warning of intrusion and a data series to size the reservoir correctly. Third, pair the reservoir with a valuation of the upstream catchments, since protecting the source is often the least costly way to keep raw water available in future dry seasons.

Sirkularium sees raw water reserves as infrastructure with a measurable economic return, and recommends that cities along tidal rivers in Kalimantan and Sumatra assess them in those terms. What to watch next: whether the reservoir moves from discussion to a feasibility study with the provincial government, how quickly IPA 1 returns to full operation as the rains arrive, and whether other tidal river cities adopt similar reserve planning ahead of the next dry season.

PAM Bandarmasih hourly water balance during the intrusion

Values in cubic metres per hour

ShareLinkedInWhatsAppFacebookEmail
Sirkularium

Sirkularium is a thought-leadership and advisory institution accelerating the circular transition across solid waste, water, and energy, working with government and public institutions.

In sustainable resources, Sirkularium advises on water, tailings, and ESG governance so resource projects stay credible and investable.

Related articles

Aerial view of a revegetated former mine terrace in Indonesia, young trees in rows beside an active pit, as seen in satellite-style top-down framing
Sustainable Resources

The Directorate General of Minerals and Coal says reclamation guarantees placed by mining companies have grown from about Rp17 to 18 trillion to around Rp40 trillion, with satellite imagery used to size each deposit to the land actually opened. The Ministry of Environment adds that success will be judged on the ground, not on paper.

By Sirkularium Editorial Team, 8 min read

Aerial view of a nickel processing complex in Sulawesi with stockpiles of ore and a refinery block, or nickel matte and MHP product bags at a port
Sustainable Resources

Coordinating Minister Bahlil Lahadalia has opened the option of a moratorium on new nickel smelters that produce intermediate products such as NPI, ferronickel, nickel matte and MHP, citing a global surplus of about 2.5 million tonnes. The move reframes the next phase of downstreaming around how much value each tonne of ore retains in Indonesia.

By Sirkularium Editorial Team, 8 min read

Forested slopes of Mount Tompotika in Banggai Regency, Central Sulawesi, with farmland and a village in the foreground
Sustainable Resources

The Central Sulawesi Information Commission has ruled that the environmental approvals and AMDAL documents for PT Anugerah Bangun Mamur and PT Anugerah Sumber Bumi in Banggai Regency are public information, to be shared with the Tompotika Conservation Alliance within 14 working days. The decision turns the AMDAL into a shared baseline for valuing the forests, water, and endemic wildlife of the Tompotika landscape.

By Sirkularium Editorial Team, 8 min read

Amandit Weir in Malutu Village, Hulu Sungai Selatan, with clear water flowing over the spillway and forested Meratus foothills behind
Sustainable Resources

The regent of Hulu Sungai Selatan has proposed piping clear raw water from the Amandit Weir to the Muara Banta intake that serves Kandangan. A treatment plant built for Rp16.8 billion and running at 50 of its 300 litres per second shows how much value a better source can carry.

By Sirkularium Editorial Team, 8 min read

Indonesian and Chilean delegations at a bilateral meeting in Santiago, with copper cathodes or a modern tailings facility as an alternative industrial image
Sustainable Resources

In Santiago on 1 October 2026, Deputy Foreign Minister Arif Havas Oegroseno proposed an Indonesia-Chile Green Minerals Partnership MoU covering joint industrial projects, a producer-country coalition, green mining technology, investment platforms, and the management and reuse of tailings. Chile's Foreign Minister welcomed the proposal and pledged early follow-up.

By Sirkularium Editorial Team, 8 min read

Police officers inspecting passenger bus cargo at the Bakauheni ferry terminal in South Lampung, with sealed bottles of seized evidence on a table
Sustainable Resources

Routine screening at Bakauheni Ferry Port stopped 61 kilograms of undocumented mercury labelled for gold processing, and investigators traced the shipment to a recipient in Bogor. The case shows how interrupting mercury supply complements Indonesia's Minamata commitments, and why the avoided environmental loss deserves to be valued.

By Sirkularium Editorial Team, 8 min read